What now for HS2 in Camden?

Artist's impression of London Euston Station

The Government recently announced that the HS2 project between Euston Station and Old Oak Common would be delayed by two years, as a way to try and save money.

What does this mean in Camden?

https://www.hs2.org.uk/in-your-area/local-community-webpages/hs2-in-camden/

It means that most of the work at Euston station will stop for the next two years, except for some works on a new Traction Sub Station being built to serve the Northern Line of the Underground, the new skills centre being built on the previous site of the Maria Fidelis School, and the completion of the interim taxi rank in Euston Square.

Continue reading “What now for HS2 in Camden?”

HS2 in Euston: Update 21 February

Update from HS2:

We’re writing to update you on works taking place in Euston Approaches area.

Welfare office in the northern end of Camden Cutting worksite

We need to provide a welfare and office building at the northern end of our worksite for our team constructing the Euston Approaches tunnels. ‘Welfare’ includes bathrooms, changing rooms, a kitchen, and a medical room.

We need to install this building as close as possible to the tunnel entrance, so our teams working inside the tunnels can access it during breaks, accidents, and emergencies. 

This building will also include a small office for our lead tunnelling team who will monitor and oversee our day-to-day tunnelling operations.

For further details of above works please follow the link here.

Hoarding maintenance works on Hampstead Road

Continue reading “HS2 in Euston: Update 21 February”

HS2 – Adelaide Road Update

Map showing locations of HS2 works in Camden

HS2 are having a virtual update session regarding the works at Adelaide Road, where HS2 are digging a new ventilation shaft for the new train tunnels.

Timeslots are available on Wednesday 19 October between 3 pm and 6 pm.

To book a slot, click on this link:

https://www.hs2.org.uk/events/one-to-one-virtual-events-hs2-works-at-adelaide-road-10/

For a more detailed look at upcoming HS2 works in Camden, click on the link below:

https://www.hs2.org.uk/in-your-area/local-community-webpages/hs2-in-camden/

If you have a more general query, they can be contacted at hs2enquiries@hs2.org.uk .

HS2 in Euston Update – December 2021

The following works are coming up in Euston, as given by HS2:

Demolition works to One Euston Square and Grant Thornton House Buildings, ongoing until July 2022
We completed a trial closure of access between Euston station piazza and western colonnade (where Sainsbury’s and Café Nero are) in September 2021. This has allowed us to determine if pedestrian movement through the station and the surrounding areas is acceptable. From mid-December 2021 we will permanently close this external route and put an alternative pedestrian route in place via the station and we’ll be constructing a step free access within the same area.

Please follow the link to view or download a copy of above works notification

Ongoing works at the former National Temperance Hospital site
This is a reminder and update regarding ongoing works at the above location. From December 2021 we will be undertake enabling works to remove the remaining ground obstructions in the Northern compound. This includes the removal of basement retaining walls, pile caps, piles, and redundant petrol tanks. The current footpath and hoarding will need to be re-aligned. This work is expected to continue until late 2022.

Please follow the link to view or download a copy of above works notification

Weekend trial hole survey on Hampstead Road – 4 to 5 December

  • The trial hole located in front of the access gate to SCS worksite on Hampstead Road.
  • Works need to be carried out during the weekend when the access is not required.
  • Working hours: Saturday 8am to 5pm and Sunday 10am to 4pm.
  • Further trial hole to follow from 6 to 17 December during regular working hours

Please follow the link to view or download a copy of above works notification

Interim taxi rank construction
As we progress with our enabling works, we now expect the main construction works to begin from January 2022 and continue until late 2022.

Please follow the link to view or download a copy of above works notification

We are committed to keeping you informed about the planning and delivery of the railway in your area with regular updates on progress.

  • Visit your local community webpages to find information about HS2 works and developments in your area. 
  • Use our In your area map to search current and planned HS2 works, developments and opportunities in your area.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk. 

Yours sincerely,

HS2 Community Engagement team